Karachi mayor breaks ground on Rs60m Adam Road project in Clifton

Karachi Mayor Barrister Murtaza Wahab has laid the foundation stone of a Rs60 million project to rehabilitate Adam Road in Clifton. He also outlined a wider programme of roads, bridges, flyovers and water schemes for the city.

Karachi mayor breaks ground on Rs60m Adam Road project in Clifton
Image: Asfa syed / Wikimedia Commons, CC BY-SA 4.0
At a glance
  • Rs60 million Adam Road project will rehabilitate the road from Chaudhry Khaliq-uz-Zaman Road to McNeil Road.
  • The mayor said Adam Road would be handed over to residents within three weeks.
  • Work is under way on 165 roads across Karachi under a wider road programme.
  • A bridge on Nishtar Road and new flyovers are among other projects announced.

Karachi Mayor Barrister Murtaza Wahab on Sunday laid the foundation stone of a Rs60 million project to improve and rehabilitate Adam Road in Clifton. The work on Adam Road will cover the stretch from Chaudhry Khaliq-uz-Zaman Road to McNeil Road.

Speaking at the ceremony, he said the Adam Road project fulfilled a longstanding public demand. Having visited the area for years, he said, he was aware of the difficulties residents faced.

Rs60m
cost of the Adam Road project
2,500 ft
single carriageway to be built
165
roads under construction across Karachi
Rs68bn
announced road improvement programme

What the Adam Road project includes

According to an official statement, the plan covers a single carriageway of 2,500 running feet and the development and rehabilitation of a 45-foot-wide road. A paver-block road of 500 running feet, averaging 24 feet in width, will also be built on Adam Road.

The sewerage system along the route will be rehabilitated alongside the road work. The mayor said construction had begun a day earlier and that the road would be handed over to residents within three weeks.

Karachi Metropolitan Corporation [KMC] will continue its development initiatives to provide better facilities to citizens

Barrister Murtaza Wahab, Mayor of Karachi

adam road: Key numbers
adam road: Key numbers

Wider plans beyond Adam Road

Mr Wahab said the Adam Road project was part of a broader effort to improve Karachi's road network and basic municipal services. He said Rs1.1 billion would be spent on connecting roads in Saddar Town, while work was under way on 165 roads across the city, made up of 139 roads and 26 additional schemes. These were targeted for completion within 120 days.

He recalled that a Rs68 billion programme for the city's roads had been announced at the start of the year. Work on these projects had begun, he said, and the aim was to finish them within the current financial year.

Construction of a bridge on Nishtar Road, meant to ease traffic arriving from the Lyari Expressway, has also started. It is expected to be completed within 100 days, with opening by the middle of January next year.

Karachi projects mentioned by the mayor and their stated targets
Project Details Stated target
Adam Road, Clifton Rs60m road and sewerage rehabilitation Handover within three weeks
Nishtar Road bridge Eases traffic from Lyari Expressway 100 days; opening by mid-January
Khayaban-e-Shahbaz flyover and Khayaban-e-Ittehad overhead bridge Planned Start by end-December; four to five months to build
Khaliq-uz-Zaman Road flyover Under consideration, subject to public support 100 days once work begins
Lyari elevated water line 10 million gallons per day 2027

Flyovers and water schemes

The mayor said a flyover at Khayaban-e-Shahbaz and an overhead bridge at Khayaban-e-Ittehad were planned. Work is targeted to begin by the end of December and to take four to five months.

Another flyover on Khaliq-uz-Zaman Road is under consideration. The initial design has been prepared and funds are available, he said, but public support and residents' views are essential. If people backed the idea, he said, work could begin with a 100-day completion target.

On water supply, he mentioned a 10-million-gallon-per-day elevated water line for Lyari and a similar scheme for southern areas, both targeted for 2027. A recycled-water scheme is also planned to supply industries and commercial areas, so that potable water can be kept for households.

adam road: At a glance
adam road: At a glance

Finances and political backing

The mayor said the Karachi Metropolitan Corporation (KMC) had faced severe financial constraints when the present administration took charge. Even small tasks such as building footpaths and installing streetlights had been difficult. He credited the change to the “elimination of corruption, theft and financial leakages within the institution, along with an increase in its revenue”.

He said the Pakistan Peoples Party leadership was committed to improving the city's infrastructure and services. The ceremony was attended by Special Assistant to the Chief Minister Sindh Najmi Alam, PPP Parliamentary Leader in the City Council Karamullah Waqasi, Deputy Parliamentary Leader Dil Muhammad, Nusrat Niazi, and other elected representatives and local leaders.

Adam Road explained: background to the project

The Adam Road project is a Rs60 million scheme in Clifton, Karachi. According to an official statement, it combines a 2,500-running-foot single carriageway, the development and rehabilitation of a 45-foot-wide road, a 500-running-foot paver-block road averaging 24 feet in width, and rehabilitation of the sewerage system.

The mayor described the work as the fulfilment of a longstanding public demand. He said he had visited the area for years and understood the difficulties residents faced. Construction began a day before the ceremony, and he promised that residents would receive the road within three weeks.

The scheme sits within a larger set of Karachi projects that the mayor listed, from the Rs68 billion road programme to flyovers and water lines. Those stated targets are summarised in the table above, where the Adam Road entry carries a promise of handover within three weeks.

What happens next

Work on Adam Road is under way, with handover to residents promised within three weeks. Construction of the Khayaban-e-Shahbaz flyover and the Khayaban-e-Ittehad overhead bridge is targeted to begin by the end of December. The Khaliq-uz-Zaman Road flyover will move ahead only if residents back the proposal.

adam road: In their words
adam road: In their words

Questions and answers

How much will the Adam Road project cost?

According to an official statement, the project will cost Rs60 million. It covers road construction and rehabilitation as well as work on the sewerage system.

Which stretch of Adam Road will be rehabilitated?

The work covers the section from Chaudhry Khaliq-uz-Zaman Road to McNeil Road in Clifton, Karachi.

When will the Nishtar Road bridge open?

The mayor said the bridge is expected to be completed within 100 days, with opening to the public by the middle of January next year.

When will the road be handed over to residents?

The mayor said construction had begun a day before the ceremony and that the road would be handed over to residents within three weeks.

What is the Rs68 billion road programme?

The mayor recalled that a Rs68 billion programme for the city's roads had been announced at the start of the year. Work on these projects had begun, he said, and the aim was to finish them within the current financial year.

Is the Khaliq-uz-Zaman Road flyover confirmed?

No. The mayor said it is under consideration. The initial design has been prepared and funds are available, but public support and residents' views are essential, and work could begin with a 100-day completion target if people back the idea.

What water schemes did the mayor mention?

He mentioned a 10-million-gallon-per-day elevated water line for Lyari and a similar scheme for southern areas, both targeted for 2027. A recycled-water scheme is also planned for industries and commercial areas.

Image: Asfa syed / Wikimedia Commons, CC BY-SA 4.0